Over 100 medicine providers visited the recent Eastowne mock-up in MacNider Hall, to observe the collaborative work spaces planned for the new six-story medical office building at the intersection of I-40 and US 15-501. Providers also shared valuable feedback with the Eastowne planning and design team as it prepares for an opening in Fall, 2020. Learn more about this project at www.unceastowne.org.
Construction of the new Panther Creek medical office building in Northwestern Cary between Brier Creek and Apex, near Panther Creek High School, is also progressing. The building is expected to be completed on December 18, and the new practice is scheduled to open in January, 2020. Learn more from UNC Panther Creek Medical Practice Director Helen Claire West, MD, in this interview.
(Photos provided by UNC Health Care Real Estate & Development Planning.)
Sunshades installed, canopies framed and canopy metal panels in fabrication.Curb and pavement are ongoing.
Transformer is energized and mechanical equipment install is progressing. Curb and pavement is ongoing.
Exterior finishes for the building and the gazebo perimeter framing are all progressing.
Fin metal panel installation complete, tilt walls are painted and sunshades installed.
Third floor “off-stage” area with paint ongoing and ceiling grid, diffusers and lights installed.
Third floor monumental stair near elevator shaft with finishes on-going and elevator installation commencing.
Second floor radiology suite with lead-lined drywall installed.
Second floor monumental stair with elevator shaft-wall installed and soffit and wall framing ongoing.
First floor procedure room with drywall installed and finishing ongoing.